This document reports the successful launch ceremony for the 'Jingxin Jili' pipe jacking, a key component of the Jingxin Reservoir reinforcement project, marking the project's entry into a critical 100-day construction phase.
Document Text
211 characters
10月15日下午,径心水库除险加固工程“径心尽力号”顶管始发仪式举办,市东部水源管理中心及各参建单位负责人参加仪式。 “径心尽力号”顶管为JCCP钢筒混凝土管,全长219米,管径2米。顶管施工是径心水库除险加固工程建设的关键工作。伴随着“始发”的指令响起,顶管机头迅速启动,“径心尽力号”顶管顺利始发,标志着径心水库除险加固工程进入“百日攻坚”的关键节点。(市东部水源管理中心 马丽莎)