Progress Report on Shenzhen Major Projects, January-October 2024

2024年1-10月深圳市重大项目进展情况

深圳市发展和改革委员会 fgw
This document reports the progress of Shenzhen's major projects for the first ten months of 2024, indicating that 897 major projects with a total investment of approximately 3.7 trillion yuan were arranged, and the construction projects have exceeded their annual investment target with a completion rate of 101.5%.
Document Text 102 characters
2024年全市共安排重大项目897个,总投资约3.7万亿元,其中,建设(新建、续建)项目732个,年度计划投资3238.7亿元。1-10月全市重大建设项目完成投资3285.7亿元,投资进度率101.5%。