Breakthrough of 10,000 Meters! Luo-Tie Project Tunnel Boring Task Passes Halfway Mark
突破10000米!罗铁项目掘进任务过半
深圳市水务局
swj
This document announces that the main water conveyance tunnel of the Luotian Reservoir-Tiegang Reservoir Water Conveyance Tunnel Project (Luo-Tie Project), a supporting project of the Pearl River Delta Water Resources Allocation Project in Shenzhen, has exceeded 10,000 meters of boring, marking the completion of over half the tunneling task. It highlights the project's complexity and its role in securing water supply for over 6 million residents in western Shenzhen districts.
Document Text
396 characters
2025年5月7日珠江三角洲水资源配置工程在深圳境内的配套项目罗田水库-铁岗水库输水隧洞工程(下称“罗铁项目”)主体输水隧洞累计掘进量突破10000米掘进任务过半!01迎难而上,安全掘进罗铁项目涉及下穿高铁、地铁、高速公路、地表水体等16处穿越断层破碎带12处地质条件复杂、安全风险高、技术难度大02民生工程 全力推进 罗田水库-铁岗水库输水隧洞工程是广东省重点项目,也是深圳市“两江并举、三纵四横”供水水源保障格局的“一纵”,其在地下50米至170米深处建设总长21.68千米的输水管道,将西江来水从罗田水库引至铁岗水库,沿途向罗田水厂、五指耙水厂、长流陂水厂供水。 当前,该工程3座竖井、3条交通洞、2座地下阀室均已开挖完成,主体输水隧洞施工也进入下半场攻坚阶段。待罗铁项目建成后,将保障宝安区、南山区等西部片区600余万常住人口的饮水安全,为粤港澳大湾区高质量发展提供坚实的水安全保障。
Topics
water resources
infrastructure construction
regional development
Metadata
| Publisher | 深圳市水务局 |
| Site | swj |
| Date | 2025-05-09 14:40:11 |
| Category | report |
| Policy Area | 水利工程/基础设施建设 |
| CMS Category | 工作动态 |
Verification
References (1)
|
unkn
珠江三角洲水资源配置工程
广东省人民政府关于禁止在珠江三角洲水资源配置工程东莞市配套供水项目(大溪水怀德水库扩建工程)占地及淹没区新增建 |
llm |
Citation Network
Full network →