Progress Report on Major Projects in Shenzhen, January-September 2025
2025年1-9月深圳市重大项目进展情况
深圳市发展和改革委员会
fgw
This document reports the progress of 828 major projects in Shenzhen for the first nine months of 2025, detailing a total planned investment of approximately 3.2 trillion yuan and an 85.1% completion rate of the annual investment target.
Document Text
105 characters
经增补调整,2025年全市共安排重大项目828个,总投资约3.2万亿元,其中,建设(新建、续建)项目702个,年度计划投资3337.1亿元。1-9月全市重大项目累计完成投资2841.0亿元,投资进度85.1%。
Topics
economic development
infrastructure investment
project management