Progress Report on Shenzhen Major Construction Projects (January-June 2021)
2021年1月-6月深圳市重大建设项目进展情况
深圳市公安局
ga
This document reports the progress of three major information technology construction projects under the Shenzhen Public Security Bureau for the first half of 2021, detailing total investment, annual planned investment, and the amount completed.
Document Text
119 characters
2021年深圳市公安局信息化项目共安排重大建设项目3个,总投资86353.5万元。此3个重大建设项目均为续建项目,年度计划投资22900万元。今年1月-6月,3个重大建设项目累计完成投资2198.7051万元,完成年度计划投资的9.6%。